Schedule

2017

  • Environmental Assessment Completed and FONSI Acquired (Finding of No Significant Impact)

2018

  • Early: Project Team Established and Public Involvement Begins for Next Phase (Elected Officials Briefing, Community Advisory Group Meeting, Public Meeting)
  • Summer: Missouri Highways and Transportation Commission Approves Project for Design-Build

2019

  • Summer: Project Goes Out to Contractors for Bidding
  • Construction Begins
I-270 North Timeline
Enlarged View Project Schedule